Capital Projects

Print
Press Enter to show all options, press Tab go to next option

Public Utilities Department

1. Marycrest Phase III B Water Main Improvements
    Reconstruction of the water main on Hammes Avenue (Capri-Jefferson), Kathlyn Place (St. Jude-South End),                Notre Dame Avenue (Capri-Hammes) & St. Jude Avenue (Capri-North End)
    Construction will start April 16th and to be completed by October
    Construction cost: $1,732,807.65
    Contractor: Brandt Excavating
    City contact: Ryan Liang 815-724-4230

 

2. 3001-3009 Heritage Drive Water Main Improvements
    Rehabilitation of the water main between 3001 & 3009 Heritage Drive
    Construction will start April 18th and to be completed by June
    Construction cost: $69,999.99
    Contractor: Construction by Camco
    City contact: Ryan Liang 815-724-4230

 

3. Jefferson Street / Essington Road Water Main Improvements
    Rehabilitation of the water main on Essington Road (Twin Oaks-Jefferson) & Jefferson Street (Essington-Houbolt)
    Construction will start the end of April and to be completed by September
    Construction cost: $672,416.40
    Contractor: Construction by Camco
    City contact: Ryan Liang 815-724-4230

 

4. Marycrest Phase III A Water Main Improvements
    Reconstruction of the water main on Joseph Avenue (Francine-St. Francis) & Webster Avenue (Hammes-Joseph)
    Construction will start the middle of May and to be completed by October
    Construction cost: $779,685.12
    Contractor: Len Cox & Sons Excavating
    City contact: Ryan Liang 815-724-4230

 

5. Raynor Park Phase I Water Main Improvements
    Reconstruction of the water main on Burry Street (Curtis-Theodore), Catherine Street (Ingalls-Theodore), Curtis          Avenue (Catherine-Hosmer) & Norley Avenue (Catherine-Hosmer)
    Construction will start the middle of May and to be completed by September
    Construction cost: $1,376,704.33
    Contractor: Len Cox & Sons Excavating
    City contact: Ryan Liang 815-724-4230

 

6. Schriber Avenue Water Main Improvements
    Reconstruction of the water main on Schriber Avenue (Catherine-Dawes), Donnie Court (Schriber -North End) &         Ronnie Court (Schriber -North End)
    Construction will start the middle of May and to be completed by August
    Construction cost: $367,154.36
    Contractor: Stip Brothers Excavating, Inc.
    City contact: Ryan Liang 815-724-4230

 

Public Works Department

The Essington Road Bridge over the Rock Run Creek will be replaced in 2020 by the Public Works Department. Currently, there is no bridge work underway, but there is utility relocation work in progress.